Hi,
Capital Projects are Investment Type of Project where in Asset is created in Integration with Investment Management.
The Main Purpose of Investment Management is for Reporting at Higher Level and Creation of (Asset Under Construction)
Asset Automatically..
Settllement is carried out to post Project Actual Costs on Asset.
You need to create Investment Program and Investment Profile form IM side.
you need to do cost planning through CJ40.
Budgeting using IM34.IM32,IM52
Rest process is same as explanied by Sukhveer
Only Funds Management is not a must, only if you want to track Project Expenses
Regards,